01
Executive
Overview
At Riyadh Front Mall, AFAQ delivered a complete turnkey media façade for VOV Gaming — one of the Kingdom’s most dynamic e-gaming venues. Under a single-source EPC contract we engineered, fabricated and integrated 550m² of high-resolution LED panels across the building façade, with custom structural steel sub-frames designed to the Saudi Building Code, certified load analysis, and full data/power distribution — from pixel to steel, to client handover.
02
Project Snapshot
Client / Owning Entity
PIF / SAVVY
Location
Riyadh Front Mall, Riyadh
Project Type
AV Integration & Steel
Engineering Services
dvLED Media Façade · Structural Steel Sub-frames · Data & Power Distribution · Content Control
Industry Sector
Entertainment & Mega Events
03
The Engineering
Challenge
A building-scale media façade demanded custom structural steel sub-frames designed to the Saudi Building Code with certified load analysis.
A single-source EPC contract placed engineering, fabrication, integration and handover under one line of accountability.
04
The AFAQ Solution
Engineering & Load Analysis
Certified load analysis and steel design to the Saudi Building Code.
Steel Fabrication
Custom structural steel sub-frames fabricated to tolerance.
LED Integration
550m² of high-resolution LED panels integrated across the façade.
Distribution & Handover
Full data and power distribution, commissioned to client handover.
05
Scope of Work
Media Façade Engineering
End-to-end engineering of the LED façade system.
Steel Sub-frame Fabrication
Custom sub-frames to the Saudi Building Code.
LED Panel Integration
550m² of high-resolution panels across the building.
Data & Power Distribution
Full distribution with content control.
Technologies Used
- Key Deliverables
- Design-ready terrain models
- AutoCAD Civil 3D deliverables
- GIS dataset
06
Project Highlights
Single-source EPC
SBC-certified steel
High-resolution façade
Pixel-to-steel integration
08
Project Metrics
>2mm
Steel Tolerance
1
EPC Contract
SBC
Certified Steel
02